Busbar Processing & Installation: Your Ultimate Guide

I. Subject Content and Applicable Scope

These guidelines apply to the busbar processing and installation of all low-voltage switchgear and power distribution boxes produced by our factory. Apart from the electrical clearance and creepage distance, other principles can also be used for high-voltage cabinets.

II. Selection of Busbars

Busbars should be selected based on circuit current, under long-term permissible temperature rise conditions and dynamic thermal stability requirements. They should be either aluminum or copper busbars and copper core plastic wires.

The selected busbars must comply with the standards GB5584-85 “Aluminum Busbars” and GB55852-85 “Copper Busbars. Consideration should also be given to the impact of heat dissipation conditions on load capacity when vertically placed (good) versus horizontally placed (poor).

If the user has other requirements, the appropriate busbar should be selected according to those requirements.

1. Common busbar specifications and current carrying capacity are shown in Appendix A1

2. Copper core plastic wires are shown in Appendix A2

III. Materials, Equipment, and Tools

1. Various specifications of bolts, nuts, washers, and copper and aluminum joints

2. Bend row cutting machine, punch press, drill press and drill bits, manual bending machine, bench vise, socket wrench, strap wrench, spanner wrench, file, scriber, steel tape measure, square ruler, steel ruler, electrician knife, screwdriver, wire pliers, hand drill, etc.

IV. Processing Steps and Technical Requirements

1. Before processing the busbar material, it should be subjected to an external inspection. If surface cracks, blemishes, pits, or miscellaneous deposits are found, or if there are large pores on the surface (aluminum busbar diameter greater than 5mm, depth greater than 0.55mm, copper busbar diameter greater than 5mm, depth greater than 0.15mm), that section should be cut off.

2. The entire busbar should be basically straight before cutting. If there is obvious unevenness or straightness, it should be corrected.

3. Cut according to the drawing or template size (for example, cut on the cutting machine or punch press) and remove burrs during processing.

After cutting, if it is found to be uneven, not straight or twisted, it should be corrected with a wooden hammer or similar tool. After correction, there should be no obvious hammer marks on the busbar.

4. Bend the busbar according to its own requirements or the specific requirements of the switch cabinet. When the busbar is bent, care should be taken not to use too much force or speed to avoid cracking. The bending degree of the two parallel busbars of the same phase should be consistent.

See also  Eliminating Structure Defects in High Carbon Chromium Bearing Steel

    (1) The minimum allowable radius for busbar bending is shown in Appendix A3.

    (2) No cracks are allowed after the busbar is bent.

    (3) The bending points of the same group of busbars should be basically consistent after installation.

5. Busbar Hole Drilling

(1) The pairing of the busbar hole and bolt specifications is selected according to Appendix A4.

(2) After determining the hole size according to the used busbar specifications, overlapping form, and electrical pile head form, drill or punch holes on a drilling machine or punch press.

(3) After the busbar is processed, cut-offs and hole edges should be deburred and chamfered.

6. Both the connection points between busbars and between busbars and electrical pile heads should be tinned and crimped, with neutral Vaseline applied to the tinned connection parts. Depending on the plant’s technical conditions, conductive paste can be used instead of tinning.

(1) For detailed busbar tinning procedures, refer to the “Tinning Process Guidelines”. For application of conductive paste, refer to the “Conductive Paste Application Guidelines”.

(2) Busbar crimping should be done using a dedicated crimping mold on a punch press.

(3) Before crimping, the crimping boundary should be marked (generally 20mm from the connection edge).

7. All busbars should be painted black. The painted edges should be basically on one line, without missing paint, drip marks, foreign objects, or other traces. The overlapping surface should not be painted, and the distance between the painted edge and the overlapping edge should be between 5-10mm.

V. Busbar with Copper-core Plastic Wires

Busbars with a rated current below 200A can be replaced with copper-core plastic wires, with copper/aluminum connectors crimped on both ends.

The stripping length and selected connectors are shown in Appendix A5. The exposed part of the crimping area should be wrapped with insulating tape.

VI. Busbar Installation

1. Before installing the busbar, inspect the quality of the busbar and its accessories. Unqualified items are not allowed to be installed.

2. When the busbar is long (generally low voltage cabinet >0.8M, GCK >0.4M), a suitable busbar clamp and insulator should be used for fixing in the middle.

See also  5 Surprising Application Industries for Industrial Robots You Need to Know

3. When the main busbar overlaps, the three phases must be staggered layer by layer and not crossed. When two or more busbars are used in parallel for the same phase, there should be a row’s thickness of space between the two (to increase the heat dissipation area).

4. During installation, the overlapping surfaces of the busbar to busbar and busbar to electrical pile head must be naturally flat. No external force should be used to press it flat, causing stress on the busbar, affecting the switch components, and the busbar’s dynamic thermal stability.

5. After tightening the bolts, there must be sufficient contact pressure between the overlapping surfaces. The contact tightness can be checked with a 0.05x10mm feeler gauge.

For busbars wider than 63mm, the depth of insertion in any direction should not exceed 6mm. For those less than 56mm, the depth of insertion should not exceed 4mm. The bolt head should protrude 2-5 threads from the nut (after tightening). It should not be too short or too long.

6. When the busbar is placed flat, the bolt should be inserted from top to bottom. When vertical, it should be inserted from front to back, that is, the nut should be placed on the back.

7. If there are difficulties in the contact area or layout, a transition bar connection can be added as needed.

8. The main busbar must be firmly clamped with a busbar clamp.

9. Except for special circumstances, busbars should be installed according to drawing requirements. Their layout and installation must ensure the electrical clearance (≥12mm) and creepage distance (≥14mm) between the busbar and other components and elements, auxiliary parts.

The minimum requirements for electrical clearance and creepage distance also meet the values specified in Table A8. It also meets the requirements for arc spraying distance (see “Electrical component, auxiliary installation, tuning process rules”).

10. For all horizontal busbars, vertical busbars, branch busbars, and live parts between main circuit connectors in drawer cabinets, and their electrical clearance and creepage distance from grounded metal parts, the rated voltage should be between 380V-660V and should not be less than 20mm.

Insulation wrapping, insulation sleeving, epoxy powder spraying or other insulation materials are allowed to be used as the insulating layer of the busbar to reduce the requirements for busbar clearance, but it should still meet the provisions of Table A8.

See also  Zinc Alloy Die Casting Basics You Should Know

11. For other forms of low-voltage switchgear, the electrical clearance and creepage distance between main circuit busbars should also refer to the provisions of Article 10 when the dynamic thermal stability current passes through and may cause a reduction in electrical clearance.

12. See Appendix A6 for the typical connection forms and requirements of busbar overlaps.

VII. Apply Sequence Markers

After the busbar is installed, phase sequence signs should be affixed in a prominent position on the busbar, or three-color paint blocks should be painted to indicate the phase sequence (Phase A: yellow; Phase B: green; Phase C: red).

(1) See Appendix A7 for the phase sequence arrangement of the busbar in the cabinet.

VIII. Quality Inspection

(1) Check whether there are cracks at the bend of the busbar and whether the surface is smooth.

(2) Check whether the tinning place of the busbar is smooth, bright, and uniform, and use a feeler gauge to check whether the gap between the busbar overlapping surfaces meets the requirements.

(3) Check whether the busbar is firmly installed and overlapped, whether the layout is beautiful, and whether it meets the requirements for electrical clearance, creepage distance, and arc spraying distance.

(4) Whether the phase sequence mark is correct.

Appendix A1  Single rectangular busbar specifications and current carrying capacity.

Copper Busbar TMY
Busbar Cross-Section(㎜2Maximum Permissible Current (A)
Horizontal PlacementVertical Placement
Specification     Area25℃40℃25℃40℃
15×345200167210171
20×360261212275224
25×375323263340277
30×4120451368475387
40×4160593483625509
40×5200665541700570
50×5250816665860700
50×6300905738955778
60×636010698931125916
60×84801251101913201075
60×106001395113614751202
80×64801360110814801206
80×8640553126516901377
80×1080017847142319001548
100×66001665135618101475
100×88001911155720801695
100×1010002121172823101882
120×89602210181024001956
120×1012002435198426502159

Appendix A3: Minimum radius (R) for busbar bending (flat bend) (busbar thickness b)

MATERIAL/SpecificationsTMLLMY
≤5×50R=2bR=2b
>5×50R=2bR=2.5b

Appendix A4: Busbar, Bolt Hole, and Diameter Fitting

Bolt DiameterBusbar HoleBolt DiameterBusbar Hole Diameter
M6¢6.5M12¢13
M8¢9M16¢18
M10¢11  

Appendix A5

Terminal (mm)Wire Stripping Length (mm)
1010
1612
2514
3516
 16

Note: Single-core wires less than 10mm can be installed directly using the bending circle method.

Appendix A7 Wire phase sequence arrangement

Arrangement Method/Phase SequenceVerticalHorizontalFront and BackSign Color
ATopLeftFarYellow
BMiddleMiddleMediumGreen
CBottomRightNearRed
Neutral LineVery BottomFinallyClosest 

Note: The above is observed from the front of the cabinet. (Special cases may not follow this table, but must be marked)

Appendix A6  Dimensions of Bolt Connection Holes for Rectangular Busbars

LegendDimensions (mm)Components
ABDFECDiameterBoltNutWasherSpring Washer
 15
20
25
30
40
40
50
50
60
80
10
12
12
15
20
  20
26
26
30
40
7
11
11
13
13
M6
M10
M10
M12
M12
2242 
 50
60
75
90
14.5
17
14
17
22
17
23
28
13M123363 
 80
100
80
100
    17M164486
 15
20
25
20
25
25
35
40
30
40
15
15
15
20
20
25
25
25
30
30
    7
7
7
11
11
11
11
11
13
13
M6
M6
M6
M10
M10
M10
M10
M10
M12
M12
1121

Appendix A6 (2) Hole Size for Rectangular Busbar Bolt Connection

LegendDimensions (mm)Components
ABDFECDiameterBoltNutWasherSpring Washer
 40
50
60
60
40
50
50
60
11
14
14
17
11
14
17
17
18
22
26
26
18
22
22
26
11
13
13
13
M10
M12
M12
M12
2242
 30
40
30
30
40
40
50
50
50
50
60
60
60
60
80
80
80
80
100
100
100
12
12
15
20
15
20
20
25
30
40
30
25
30
40
30
40
50
60
40
50
60
 7
10
7
7
10
10
12
12
12
12
15
15
15
15
20
20
20
20
20
25
25
25
16
20
16
16
20
20
26
26
26
26
30
30
30
30
40
40
40
40
50
50
50
 5.5
5.5
7
7
7
7
11
11
11
11
11
11
13
13
13
13
13
13
13
13
13
M5
M5
M6
M6
M6
M6
M10
M10
M10
M10
M10
M10
M12
M12
M12
M12
M12
M12
M12
M12
M12
2242
 80
80
100
80
80
100
    17M 164484

Appendix A8 Electrical Clearance, Creepage Distance, and Spacing Distance (mm)

Rated Insulation Voltage(V)Electrical ClearanceCreepage Distance
63A and belowMore than 63A63A and belowMore than 63A
V≤603535
60<V≤3005668
300<V≤6608101012

Minimum distance between primary circuit electrical equipment and the ground.

 3KV6KV10KV35KV
The distance between bare conductors of different phases and between bare live parts to the grounded frame.75100125300
The distance from the live part of the bare conductor toFront Metal Cover Plate105130155330
Transmission Rod Bare Belt100120130320
The portion of the energized bare conductor to the mesh sealing plate or mesh door175200225400
Height of the unshielded bare conductor to the ground (floor) slab2500250025002500

Get Expert Advice

Let our experts help you choose the right metalworking machine

About The Author

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top